Oracle on the hook to pay data centre investors even if site has no electricity

158 points · 154 comments · Betelbuddy

  1. jpster · · focus · HN ↗
    I thought force majeure is for weather catastrophes, natural disasters, terrorism, “acts of God”. Not for “we didn’t get the permits”.
    1. jasomill · · focus · HN ↗
      You'd have to read the contract.

      And it depends on why they didn't get the permits.

      Miss a deadline for filing? Not force majeure.

      Permit that was reasonably expected to be granted denied due to a major shift in public policy? Possibly force majeure.

      Power companies refuse to provide service due to a decline in overall capacity or spike in overall demand not reasonably foreseeable by the contracting parties? Possibly force majeure.