Oracle on the hook to pay data centre investors even if site has no electricity
Unofficial Hacker News client; not affiliated with Y Combinator.
jrochkind1 · · focus · HN ↗
You keep saying those words, I do not think they mean what you think they mean.
Like, if Oracle is trying to get out of contractual obligations due to "force majeure", but claiming it doesn't mean there's any change to delivery expectations... I don't think that's going to work very well for them in court if someone takes it there? (Although it maybe wouldn't have anyway, so they maybe don't care about adding BS on top of BS?)
cmiles74 · · focus · HN ↗